Special Considerations while aligning Highways on hilly areas

The position or the layout of the center line of the highway on the ground is called the alignment. The horizontal alignment includes the straight path, the horizontal deviations and curves.

 Changes in gradient and vertical curves are covered under vertical alignment of roads.



Highway Leading through mountains towards National Park Canada


A new road should be aligned very carefully as improper alignment would result in one or more of the following disadvantages :-
  • # Increase in construction cost
  • # Increase in maintenance cost
  • # Increase in vehicle operation cost
  • # Increase in accident rate

Once the road is aligned and constructed, it is not easy to change the alignment due to increase in cost of adjoining land and construction of costly structures by the road side. Hence the importance of careful considerations while finalizing the alignment of a new road need not be over emphasized.

Stability 

While aligning hill roads, special care should be taken to align the road along the side of the hill which is stable. A common problem in hill roads is that of land slides. The cutting and filling of earth to construct roads on hill-side causes steepening of existing slopes and effect its stability.

Drainage


Numerous hill side drains should be provided for adequate drainage facility across the road. But the cross drainage structure being costly, attempts should be made to align the road in such a way where the number of cross-drainage structures are minimum.

Geometric standards of hill roads


Different sets of geometric standards are followed in hill roads with reference to gradient, curves and speed and they consequently influence the sight distance, radius of curve and other related features. The route should enable the ruling gradient to be attained in most of the length, minimizing steep gradients, hair pin bands and needless rise and fall.

Resisting length

The resisting length of a road may be calculated from the total work to be done to move the loads along the route taking the horizontal length, the actual difference in levels between the two stations and the sum of ineffective rise and fall in excess of floating gradient. In brief, the resisting length of the alignment should be kept as low as possible. Thus the ineffective rise and executive fall should be kept minimum.



Comments

Popular posts from this blog

Google Input Tools Nepali Google Input Tools Nepali   allows you to type in Nepali language. Google Transliteration IME is an input method editor that enables users to use a Roman keyboard to input text into Nepali languages. Google Input Tool Nepali is the best way of typing the Nepali language on the user's computer. Google Input Tools Nepali is easy to use online as well as offline. Users can use Latin characters to type any word they want, and Google IME translates them with 100% accuracy. 👉  google input tools Nepali                                                                                                                     c...

Design criteria for permeable pavement

Hydrologic design considerations Permeable pavement is subject to the following design considerations, including benefits and constraints. Available space – A significant advantage of permeable pavement is its ability to combine detention/ infiltration and pavement, thereby reducing or eliminating land required for detention facilities. This is especially important in urban areas with high land prices and highly developed sites with little or no space for stormwater detention. Soils – Soil conditions and infiltration rates determine the use of an  underdrain . ( NRCS   Hydrologic Soil Group  (HSG) C or D soils usually require an underdrain, whereas HSG A and B soils often do not.) Designers should evaluate existing soil properties during initial site layout with the goal of configuring permeable pavement that conserves and protects soils with the highest infiltration rates. In particular, areas of HSG A or B soils shown on soil surveys should be considered as pri...